Versions Compared

Key

  • This line was added.
  • This line was removed.
  • Formatting was changed.

...

If a column is editable, you can edit its value by double clicking. Assume a column is editable unless noted otherwise in this section.

The 5D column toggles whether the task is active in the 3D View or in the 5D cost graph

The ID column contains an ID for each task. Task IDs are unique, when a new task is created the ID is automatically set to the smallest unreserved whole number. This column can be mapped to when importing.

Displays all filters added to a task and allows you to delete them. For more information see Filters.

Specifies the task type which controls which objects can be assigned. For more information see Object Assignment.

The Obj # column displays the number of objects assigned to the task. It also includes the number of objects assigned to the children of the task in parenthesis. This column cannot be edited directly.

The Name column displays a unique name for the task. This column can be mapped to when importing.

The Duration, Start and End columns describe the amount of time that the task is elapsed. These columns have planned, actual, remaining, and baseline counterparts. These columns can be mapped to when importing with the exception of the Highlight columns.

The Progress Status column controls whether a task has started or been completed.

The % Complete column displays the completion status of a task. This column cannot be edited directly.

There are also Planned, Actual, Remaining, and Baseline columns for each type of cost.

The Predecessor column can be used to assign predecessors. The Successor column can be used to assign successor. For more information see 4D Analysis.

The Resource column is used to assign resources to tasks. For more information see 5D Construction.

The Constraint Type column displays the type of constraint. By default, all tasks have the as soon as possible constraint forcing them to start at the beginning of the schedule. Changing the start date will change the constraint type to no earlier than.

The Constraint Date column displays the date of the constraint.

The Source column displays the original source of the schedule. Possible sources are P6, Microsoft Project, or if created natively, Fuzor. This is not editable in Fuzor.The Calendar column allows you to assign a specific calendar for each task.

The Total Float/Slack column is the amount of time the task can miss its completion date without effecting the project completion dates.