Learn best practices to update import and update schedules using XML format
...
It is important to know how your schedule is imported from your authoring software. Some Fuzor Columns have no counterparts in authoring software and are for internal use. If a particular column does not have a counterpart in a particular authoring software it is possible that it may still be populated on import. When Using Asta Powerproject is it recommended that the user export to an XML in either Primavera P6 or Microsoft Project Format. Unless importing costs. Costs from Microsoft project are better imported through column mapping. |
Identifiers | |||
Fuzor | Primavera P6 | Asta Powerproject | Microsoft Project |
ID | Activity ID or WBS Code | No Counterpart | No Counterpart |
Name | Activity Name or WBS Name | Name | Task Name |
Durations | |||
Fuzor | Primavera P6 | Asta Powerproject | Microsoft Project |
Duration | At Complete Duration | Duration | Duration |
Planned Duration | Original Duration | Original Duration | No Counterpart |
Actual Duration | Actual Duration | Actual Duration | Actual Duration |
Remaining Duration | Remaining Duration | Duration Remaining | Remaining Duration |
Date Sets | |||
Fuzor | Primavera P6 | Asta Powerproject | Microsoft Project |
Start / End | Start and Finish | Start and Finish | Start and Finish |
Planned | Planned | Original | No Counterpart |
Remaining | Remaining Early | No Counterpart | No Counterpart |
Actual | Actual | Actual | Actual |
Cost Types | |||
Fuzor | Primavera P6 | Asta Powerproject | Microsoft Project |
Labor | Labor or Role | Not supported | Work |
Equipment | Non-Labor | Not supported | No Counterpart |
Expenses | Expenses | Not supported | No Counterpart |
Material | Material | Not supported | Material |
Resources | |||
Fuzor | Primavera P6 | Asta Powerproject | Microsoft Project |
Per Use Price | No Counterpart | Not supported | Per Use Cost |
Overtime Price | Overtime Factor | Not supported | Overtime Cost |
Unit Price | Price / Unit | Not supported | Std. Rate |
Budgeted Units | Planned or Budgeted Units | Not supported | No Counterpart |
Actual Units | Actual Units | Not supported | No Counterpart |
Remaining Units | Remaining Units | Not supported | No Counterpart |
At Completion Units | At Completion Units | Not supported | Units |
Logic and Special Columns | |||
Fuzor | Primavera P6 | Asta Powerproject | Microsoft Project |
% Complete | Duration % Complete | Percent Complete | % Complete |
Constraint Type | Primary Constraint Type | Constraint | Constraint Type |
Constraint Date | Primary Constraint Date | Start Constraint Date or Finish Constraint Date | Constraint Date |
Task Calendar | Activity Calendar | Calendar | Task Calendar |
Total Float/Slack | Total Float | Total Float | Total Slack |
...