In the realm of large scale construction it is standard to maintain a full project lifecycle schedule usually spanning several years. Relatively speaking, optimal output from Fuzor requires Micro Scheduling, a more detailed and specific scheduling of tasks.

To make a realistic schedule with Fuzor, tasks must be broken down into individual operations. When this is done properly it allows for a holistic and approach to project planning. IDD Teams can perform a detailed and visual audit of the construction simulation before the project begins. This is an opportunity to avoid scheduling issues, safety hazards and modeling errors.

A holistic approach to schedule integrations allows for faster and more accurate turn around time for a an ensuing construction simulation audit. After loading new schedule data, each detailed step in a procedure can be reviewed with the revision to the schedule.

Because schedule updates are so integral to Fuzor Project management it is important for a Fuzor user to know the best practices to ensure schedule updates run smoothly.

A Macrotask is a task imported into Fuzor from another software. A Macrotask can also be created in Fuzor but is not recommended if expecting the task to update sensibly when changes are made to the Macroschedule.

A Microtask can only be created in Fuzor.

...