Learn how to assign zones to tasks.

A construction simulation may need to show where and at what times construction zones are currently active. An ideal presentation would be able reveal and show a construction zone based on schedule data.

Fuzor allows the user to create construction zones that can be controlled with the 4D schedule and added to flythrough videos.

Zones can be assigned to temp tasks to display at specific times during a construction animationsimulation.

This is a great way to show which areas of the construction site are currently active.

The Show Task List radio button toggles whether the Gantt Chart is displayed while the Construction Zone Manager is open. The Gantt Chart and the Construction Zone Manager must be displayed so that the user can select both a task and a Zone at the same time.

Enable Zone Edit must be active in order to remove or add selected zones to tasks.

Adds the zone selected in the Contsruction Zone manager to the selected temp task. When added to a temp task zones displays during the duration of the task.

...