Assigning resources to tasks is a great way to populate cost data. Additionally when schedules are imported from authoring software resources assignments are interpreted into our system. As a result understanding how to manage the resource assignments is useful even when creating resource in authoring software and importing them into Fuzor.

When a resource is selected in the Resources List, tasks with that resource assigned appear in the Resource Tasks List.

Removes the associated resource assignment.

The Resources column in the gantt displays the primary resource assigned to the task. When selected the Task Resources menu is open. The task Resource menu allows the user to assign resources and control how much of each resource is added to the associated task.

Each of the columns in Task Resources are the same columns in the Resource Tasks List. These values can be edited from either menu. The default value for these columns is set in the Resources List but can also be viewed when adding a resource to a task.

The Add button opens a menu to list available resources to select from and add to the current task.

The Close button closes the window.

The Remove button removes the currently selected resource from the task.

Image RemovedImage Added

Resources created using automatic Category resources are automatically assigned and displayed in both the Task Resources and the Resource Tasks Menus.

...

Image Removed

The Line Graph displays the value of various cost metrics with lines over the duration of the selected dates. Use the Line Graph Settings to select which metrics should appear in the graph.

The Show Planned checkbox toggles whether the graph displays the planned line, which describes project baseline planned costs spread over the project baseline planned dates.

Image Added

The Show Actual checkbox toggles whether the graph displays the actual line, which describes active schedule actual costs spread over the actual dates.

The Show at Completion value toggles whether the graph displays an additional line describing actual values, except it also includes the remaining costs spread over remaining dates.

The Show Earned Value checkbox toggles whether the graph displays project baseline planned costs multiplied by % complete spread over the active schedule actual dates.

The Accumulate Cost checkbox toggles whether costs preceding the start date of the graph are included.

Bar Graph

This section provides detailed information on the settings associated with the Bar Graph

...