Learn best practices to update import and update schedules using XML format
...
Identifiers | |||
Fuzor | Primavera P6 | Asta Powerproject | Microsoft Project |
ID | Activity ID or WBS Code | No Counterpart | No Counterpart |
Name | Activity Name or WBS Name | Name | Task Name |
Durations | |||
Fuzor | Primavera P6 | Asta Powerproject | Microsoft Project |
Duration | At Complete Duration | Duration | Duration |
Planned Duration | Original Duration | Original Duration | No Counterpart |
Actual Duration | Actual Duration | Actual Duration | Actual Duration |
Remaining Duration | Remaining Duration | Duration Remaining | Remaining Duration |
Date Sets | |||
Fuzor | Primavera P6 | Asta Powerproject | Microsoft Project |
Start / End | Start and Finish | Start and Finish | Start and Finish |
Planned | Planned | Original | No Counterpart |
Remaining | Remaining Early | No Counterpart | No Counterpart |
Actual | Actual | Actual | Actual |
Cost Types | |||
Fuzor | Primavera P6 | Asta Powerproject | Microsoft Project |
Labor | Labor or Role | Not supported | Work |
Equipment | Non-Labor | Not supported | No Counterpart |
Expenses | Expenses | Not supported | No Counterpart |
Material | Material | Not supported | Material |
Resources | |||
Fuzor | Primavera P6 | Asta Powerproject | Microsoft Project |
Per Use Price | No Counterpart | Not supported | Per Use Cost |
Overtime Price | Overtime Factor | Not supported | Overtime Cost |
Unit Price | Price / Unit | Not supported | Std. Rate |
Budgeted Units | Planned or Budgeted Units | Not supported | No Counterpart |
Actual Units | Actual Units | Not supported | No Counterpart |
Remaining Units | Remaining Units | Not supported | No Counterpart |
At Completion Units | At Completion Units | Not supported | Units |
Logic and Special Columns | |||
Fuzor | Primavera P6 | Asta Powerproject | Microsoft Project |
% Complete | Duration % Complete | Percent Complete | % Complete |
Constraint Type | Primary Constraint Type | Constraint | Constraint Type |
Constraint Date | Primary Constraint Date | Start Constraint Date or Finish Constraint Date | Constraint Date |
Task Calendar | Activity Calendar | Calendar | Task Calendar |
Total Float/Slack | Total Float | Total Float | Total Slack |
...