The best way to import data from Primavera P6 into Fuzor is using XML. Fuzor can automatically read Primavera P6 XMLs and populate data in the Fuzor schedule based on the information.

Identifiers

Fuzor Counterpart

Name

ID

Primavera P6

Activity Name or WBS Name

Activity ID or WBS Code

Durations

Duration

Planned Duration

Actual Duration

Remaining Duration

At Complete Duration

Original Duration

Actual Duration

Remaining Duration

Date Sets

Start / End

Planned

Remaining

Actual

Start and Finish

Planned

Remaining Early

Actual

Importing Baselines

This section provides detailed information about importing baselines from Primavera P6

...