This chapter provides project management workflows that enable Microtasks micro tasks to automatically update when new schedule is loaded.

...

In the realm of large scale construction it is standard to maintain a full project lifecycle schedule usually spanning several years. Relatively speaking, optimal output from Fuzor requires Micro Schedulingmicro scheduling, a more detailed and specific scheduling of tasks.

To make a realistic schedule with Fuzor, tasks must be broken down into individual operations. When this is done properly it allows for a holistic and approach to project planning. IDD Teams can perform a detailed and visual audit of the construction simulation before the project begins. This is an opportunity to avoid scheduling issues, safety hazards and modeling errors.

A holistic approach to schedule integrations allows for faster and more accurate turn around time for a an ensuing construction simulation audit. After loading new schedule data, each detailed step in a procedure can be reviewed with the revision to the schedule.

Because schedule updates are so integral to Fuzor Project project management it is important for a Fuzor user to know the best practices to ensure schedule updates run smoothly.

A Macrotask Fuzor enables users to control this by clearly defining the difference between tasks that are imported from other software and should be updated directly by a schedule update and tasks created in Fuzor.

A Macro Task is a task imported into Fuzor from another software. A psuedo Macrotask macro task can also be created in Fuzor unders specific conditionsA Microtask but is not recommended if expecting the task to update sensibly when changes are made to the macro schedule.

A Micro Task can only be created in Fuzor. macro tasks have special scheduling logic that responds to the macro task they are linked to.

Creating the

...

Micro Schedule

Learn how to start creating the a detailed Microschedule in Fuzor

...

micro schedule in Fuzor

Handling Specific Update Cases

Learn how to use different Linking Methods and Schedule Update Methods to Properly manage a project in different schedule update situations.

Base Update Case : To understand the other cases of schedule updates. We first need to understand what the most simple update case is:

  • Microtasks and Macrotasks exist in the Fuzor Project.

  • Tasks In both the original and the Update XML have the same ID, Unique ID if using Microsoft Project.

  • Manually schedule tasks is unchecked in the Fuzor Construction Settings.

  • Autofill duration is checked in the Fuzor Construction Settings.

  • Changes to durations Macrotasks are not expected to reflected in Linked Microtasks.

  • New Calendars, Baselines, and Activity Codes are not needed or unchanged in the update.

  • The data date is not changed.

  • We are expecting dates and durations of the Microtasks to be offset by the change in dates and durations of macrotask it is linked too.

If the schedule update meets the above parameters any Update workflow and Linking method is appropriate and Microtasks will update as expected with their associated relationship.

Changes to Calendars the Data Date and Resources: Both Calendars and the Data Date can effect dates and durations of tasks in the project. If these are not imported or updated during a schedule update it is possible that the dates in your Fuzor Project are inconsistent with that of your authoring software.

Resources may affect cost calculations. If these are not imported or updated during a schedule update it is possible that the costs in your Fuzor project are inconsistent with that of your authoring software.

An XML update is needed to update or import new Calendars and Resources, Update the Data Date, or change resource and calendar task assignments and allocation. However, Column Mapping can be used to update incorrect costs directly and handle them as edited total costs.

Changes to Activity Codes : blash balsh XMLS are needed for the activty codes

Manually Schedule Tasks : If manually schedule tasks is enabled Fuzor does not respect any logic in the schedule. This means that neither Task Linking Method will update Microtasks that are linked to updated Macrotasks.

If substantial lag is introduced early in critical path the result would be an project where Microtasks are occuring far before Macrotasks that they are linked too.

There are a few common reasons why a user might enable Manually Schedule Tasks

  • Manually schedule tasks was enabled for a specific task in the authoring software and the setting is needed in the Fuzor Project to ensure that the date matches for the task. This can be resolved by ensuring that the authoring software has proper logic. with respect to DCMA guidelines? CHECK THAT ONE

  • Schedule data was exported from the authoring software before conducting a proper schedule update and there is invalid data in the schedule. This can be resolved by running a schedule update before exporting the XML.

  • The user prefers having Manually Schedule Tasksenabled when scheduling in Fuzor. This can be resolved by learning to use Fuzor without Manually Schedule Tasks enabled.Fuzor does not support schedule updates for Microtasks when Manually Schedule Tasks is checked. The above issues need to be resolved in order for a Task Linking Method to be effective

    By default, micro tasks are created instead of macro tasks when using the create construction task button. A macro task needs to be selected in order to add a micro task to the schedule.

    Image Added

    Adds a construction micro task to the currently selected macro task. Other Task Types also create micro tasks, by default.

    When a micro task is created it is created as the child of the currently selected macro task. This allows users to clearly evaluate easily understand the relationship between the microschedule and the macroschedule.

    Image Removed

    When a schedule update is made to ‘Macrotask’ that changes the start date ‘Microtask 1’, ‘Microtask 2’ and ‘Microtask 3’ will all have their start dates micro schedule and the macro schedule. If a micro task is selected when the new task is created it will becreated as a sibiling of that task and a child of the macro task parent.

    Micro tasks update start and end dates based on the offset that is introduced to an associated macro task. If the 4D Setting, Scale Micro Task Duration is enabled micro tasks will also scale their durations when the duration of the macro task is changed.

    By default, the user cannot edit the macro schedule. Task names and dates of macro tasks appear grey instead of black. The default background color of construction micro tasks is also different. This enables the user to easily distinguish between the micro tasks and macro tasks. The default background color of construction micro

    Image Added

    When a change is made to ‘Macro Task’ that changes the start of the ‘Micro task’ Chain all start dates are adjusted by the same amount.

    There are two ways to create multiple microtasks micro tasks linked together

    Image RemovedImage Added

    Creates multiple Microtasks linked together in a chain as children of the currently selected task.

    Addtionally

    Orphaned Tasks

    Learn how to handle microtasks that are associated with macrotask that is deleted in a schedule update.

    ...

    Deleted Macrotasks : Sometimes tasks are deleted when a schedule update is made. This means that there are Macrotasks in Fuzor that do not exist in the updated XML. Depending on whether these tasks are linked to microtasks or have objects assigned, there are a few different things that we may be expecting to happen. Below are some potential expectations and the best workflow associated with that result.

    When Using Merge By ID there is an option to delete tasks with assigned objects. Macrotasks that have no objects assigned will always be deleted if not included in the XML update. the Logic Relationship the best linking method when there are many deleted tasks in the XML as Children are always deleted with their parents.

    Can be used when creating Micro or Macro Tasks.

    Micro tasks can also be created separately and manually linked together using predecessor and successor relationships.

    Relinking Micro Tasks
    Anchor
    Relinking-Microtasks
    Relinking-Microtasks

    Leran how to relink a micro task to a new macro task.

    In some situations a user may need to relink a micro task to a new macro task. This may happen due to changes in the construction methodology or because of a mistake. Additionally during schedules updates some tasks may become orphaned. Orphaned tasksneed to be relinked to a new macro task before continuing.

    Relink Microtask.PNGImage Added

    Selected to relink a micro task. All micro tasks contain the icon in the relinking column allowing you to relink them at any time.

    Orphan Relink.PNGImage Added

    Selected to relink an orphaned micro task.

    After the relinking column in the micro task is selected a macro task is needed to relink the micro task too. The same column is used to select the macro task. A different Icon is used to denote a macro task.

    Image Added

    Selected to denote the macro task that the micro task is being relinked too.

    Chains of micro tasks are always linked together. only a sequential chain can be relinked at a time. a micro task with multiple predecessors or successors cannot be relinked. Predecessors and successors may need to be temporarily removed before relinking a specific chain of tasks.

    Editing the Macro Schedule

    Learn how to edit or create a macro schedule in Fuzor

    In some situations the user may need to edit task data in the macro schedule. The user also may be creating a schedule entirely in Fuzor and does not need to use the Macro-Micro relationship.

    The Micro and Macro radio button toggle between macro and micro scheduling modes. When in the radio button is set to micro the user can only create and edit micro tasks. when the radio button is set to macro the user can edit any task, but can only create macro tasks.

    Image Added
    Image Added

    A Construction task is the only task type than can be created as a macro task. However the task type of a macro task can be changed to any Fuzor task type after it is created.

    Updating the Macro Schedule

    Learn how to update the macro schedule when working with micro tasks

    A macro schedule is updated by importing a XML or CSV or by Column Mapping a spreadsheet. For both methods micro tasks update thier durations based on changes to thier associated macro task.

    When a XML or CSV is imported the gantt chart is automatically filtered to only display tasks associated with changes to micro tasks in the schedule. During the session the update is conducted the Show Merge Changes checkbox controls whether this filter is active.

    Image Added

    The Show Merge Changes checkbox toggles whether microtasks and associated macrotasks with changes are isolated in the gantt chart.

    Importing and Updating Schedules provides general information about updating by importing entire schedules using a new XML or CSV.

    Column Mapping provides general information about updating by column mapping in data from XLSX and CSV Spreadsheets. Column mapping does not enable the Show Merge Changes filter.

    Orphaned Tasks
    Anchor
    Orphaned-Tasks
    Orphaned-Tasks

    Learn how to handle micro tasks that are associated with a macro task that is deleted in a schedule update.

    Sometimes tasks are deleted when a schedule update is made. This means that there are macro tasks in Fuzor that do not exist in the updated XML.

    When Using Merge By ID there is an option to delete tasks with assigned objects. macro tasks that have no objects assigned will always be deleted if not included in the XML update.

    When a macro task is deleted the user is prompted to decide whether they would like micro tasks with deleted macro task to automatically relink to another macro task with the closest date or if they would like to manually relink micro tasks back to the macro schedule.

    Image Added

    If manually relinking is desired any micro tasks that are children of deleted macro tasks will become orphaned.

    Orphaned micro tasks always appear at the top of the gantt chart. In order to continue working the micro tasks need to be remapped to new macro tasks. The relinking column is used for to remap the micro task to a new macro task.

    Orphan Relink.PNGImage Added

    Selected to relink an orphaned micro task. for more information see Relinking Micro Tasks.