The Exclude WBS from Sorting checkbox retains WBS when sorting by columns.

The Link Planned and Remaining checkbox toggles whether remaining durations are dependent on Planned durations.

The Show Time of Day for Date checkbox toggles whether the time of day is displayed in the task table.

The Constraints Override Links checkbox toggles whether a constraint or a task link has a higher priority when evaluating task durations.

The Update Progress with Data Date checkbox toggles whether the remaining schedule is updated with the changing of the data date.

Settings 4D with Overlapping.PNGImage Added

The Scale Micro Task Duration checkbox toggles whether micro task durations are updated as well as start and end dates when using Task Linking.

the Enable Overlapping Animation Setting toggles whether overlapping animations occur when the same objects are assigned to multiple tasks.

The Task Progress Mode dropdown menu controls how logic links are handled when a predecessor has been completed before their associated logic allows. This setting behaves like the out of sequence progress setting in P6.

The Total Float/Slack Calculation drop down menu controls how the Total Float of a given task is calculated. Start Float subtracts the Early Start from the Late Start, Finish Float subtracts the Early Start from the Late Finish. The last option uses the smallest of the two.

The Calculate Link Lag Using drop down menu specifies which calendar is used to calculate the link lag of a given predecessor relationship. The length of the lag does not count non-working days.

The Task Type radio button sets the task color based on its task type or highlight color.

The Task State radio button colors tasks based on their status at the current day.

The Emulation Mode radio buttons ensure that Fuzor handles your imported schedule properly. If using Microsoft Project or Primavera P6 make sure the associated radio button is selected.

The FZM Export settings control how task filters and subcontractor filters effect what tasks and objects are visible in the Mobile Project.

...