This chapter demonstrates key features of the 4D Simulation App. Learn how to import a schedule, manipulate task columns, and create a 4D simulation of your model.

Scroll indexterm
title4D Simulation
primary4D Simulation

The 4D Simulation App is located in the Construction tab of the Fuzor App Menu. The Ctrl + 8 hotkey opens the 4D Simulation App.

Importing and exporting options are located in the bottom panel of the 4D Simulation Toolbox.

Image Modified

Gantt Chart and Task Table

Learn how to utilize and navigate the Task Table and the Gantt Chart.

The Task Table and Gantt chart can be collapsed, expanded and opened in an external window. For more information see Workspace Management.

Image Removed
Image Added

For each task there is a row in the Task Table and an adjacent time block in the Gantt Chart. The Task Table is

generally

used to

organize tasks and

edit column data directly whereas the Gantt Chart is used to display and manipulate the schedule timeline in a visual manner. As the current date in the schedule changes the Gantt Chart scrolls.

To Scroll through tasks, rotate the mouse wheel.

To Pan through the Task Table or the Gantt Chart use the scrollbar on the bottom of each view.

To Zoom into the Gantt Chart, click and drag the timeline bar at the top of the window.

The time blocks in the Gantt Chart reflect different durations and time stamps in the task. These durations are shown using different colors for Primary and Secondary schedules.

A primary duration appears using the

Task Background Color

task backgroundcColor. Orange is the default

Background

background color for for construction tasks. A secondary duration appears teal.

Image Removed
Image Added

The Data Date is a

vertical

solid blue line in the Gantt Chart. The data date is the date on which the status of the schedule is being

determined

evaluated. Tasks with no actual durations are forced to occur after the data date.

The Current Date is a

dotted black

solid red line in the Gantt Chart. This time stamp is use for simulation. The current date controls what is being animated in the 3D view. The Current Date changes as the simulation is played through.

Auto Scroll Gantt Chart is a setting in the 4D Settings. When enabled the Gantt Chart will scroll so that a currently selected task is in view. A left click changes the current date to the end of the task. A right click changes the current date to the beginning of the task. For more information see 4D Settings.

Time Controls

This section demonstrates how to change the time in the Construction Schedule.

While the 4D Simulation App is open the Date and Time can be displayed in the top center of your window. If you select any task in the 4D Task Table the date is be updated to the Primary Start of the task. The most intuitive way is by using the time line below. Simply select a point on the time line and the schedule time is changed to the specified time. If you need a more precise control of the time, you can use the 4D Time Controls to specify exact date and time.

Image ModifiedImage Modified
Image Modified
Image Modified

Changes the various time stamps in the schedule. Possible times stamps are Current Date, Data Date, Schedule Start, and Schedule Finish.

Image Modified

Zooms into the schedule.

Image Modified

Plays the animation.

Image Modified

Zooms out of the schedule.

Image Modified

Pauses the animation.

Image Modified

Scrolls forward in the schedule. The Shift + Addition Symbol hotkey can also be used

Image Modified

Scrolls backwards in the schedule. The Shift + Subtraction Symbol hotkey can also be used.

The Simulation Speed slider sets the speed for your simulation.

The Use Duration check box allows you to set a total playback time for your entire 4D Simulation.

The Adjust Playback for Animations checkbox slows down the animation during content vehicle animations based on the durations set in the Animation Manager.

Image Modified

Schedule Organization

This section demonstrates best practices for keeping your tasks organized. Learn how to manipulate the task hierarchy, rename, and reorder tasks.

When working with an elaborate schedule it is important to be properly organized. Descriptive task names, proper Work Breakdown Structure, and clever filters will make working with complex task schedules easy. Additionally understanding the functionality and best practices for basic tasks selection greatly improves workflow speed.

Image Removed

Tasks can be selected from the Gantt Chart or the Task Table. Select multiple tasks by holding either Ctrl or Shift. Holding Shift while selecting tasks selects the task that is clicked and any other tasks that exist between the last selected task and the currently selected task, retaining any current selections. Holding Ctrl while selecting tasks previously unselected tasks selects the task that is clicked, retaining any current selections. Holding Ctrl while selecting tasks previously selected tasks unselects the task that is clicked, retaining any other current selections.

When a task is selected all assigned objects are highlighted in the 3D view. Everything is deselected if multiple tasks are selected.

To rename a task double click in name column of the task with the left mouse button.

Indenting and Outdenting tasks changes the task with respect to the Work Breakdown Structure. These settings are located on the 4D Toolbar.

Image Added
Image Modified

Indents any selected tasks. This can be used with multiple tasks selected.

Image Modified

Outdents any selected tasks. This can be used with multiple tasks selected.

Image Modified

Promotes any selected tasks. This can be used with multiple tasks selected.

Image Modified

Demotes any selected tasks. This can be used with multiple tasks selected.

Image Modified

Removes any selected tasks. This can be used with multiple tasks selected.

Image Removed
Image Added

In the example both Slab F3 and Column F3 are children of 3rd Floor whereas Roof and 2nd Floor are not.

The Work Breakdown Structure (WBS) is normally imported from

another software. WBS can be defined

an XML. See Importing and Updating Schedules. Additionally micro tasks are always created as children of an associated macro task. SeeTask Linking.

In some situations WBS level can be changed in Fuzor by indenting and outdenting tasks

. A task indented one time is the child of the closest preceding task in the top level. In the example below both Curtain Walls and CIP Structural Walls are children of Walls whereas Roof is not. WBS from external software is imported into this hierarchy

after a task is created or imported.

Collapsing a

group

WBS parent hides the children of the

group

task from the

4D Simulation App

gantt chart. This is a good way

of simplifying the content

filtering visble tasks to operate on a

larger scope

large schedule. Expanding a collapsed group will show the group’s children.

Image Removed
Image Added

Expands the associated WBS hierarchy

Image Removed
Image Added

Collapses the associated WBS hierarchy

Image Added

The Expand All button expands all WBS hierarchies.

The Collapse All button collapses all WBS hierarchies.

The task background color can be changed to increase readibility and allow users to find specific tasks quickly.

Image Modified

Opens the Task Background Color Tool. This can be used with multiple tasks selected.

Image Modified

The Task Background Color Tool changes the background color that appears in the task table for any selected tasks. Tasks must be selected before opening the Task Background Color Tool

. This is a useful tool for color coding your Task Table, increasing legibility

.

The Default Color checkbox ensures that the task is colored using the default color of the task that is determined by its type.

The Override Color allows you to select a color for the background of the task.