This section demonstrates how to use the Construction Zone Manager to create zones.

Managing Zones

Learn how to manage multiple zones and assign them to appear during the construction schedule.

Updating Zones

Learn how to update zones to control which objects they select

When using zones for filtering it is important to understand how zones function in Fuzor. Zones are designed to contain a snapshot of a model. A zone is associated with the objects that are visible in the model and contained within the zone when it is created, edited or updated. This allows the user to create separate sets of zones for different model sets or sequences.

When highlight a zone will highlight the objects it is associated with and not necessarily what is visible in the scene at the time.

A user may need to update a zone in order for it to select new objects.

The Update Zones button in the 4D toolbox updates all the zones in the project. all zones are updated to associate with objects that are currently visible in the model and contained within the zone .

Adding Zones to Tasks

Learn how to assign zones to tasks.

Zones can be assigned to temp tasks to display at specific times during a construction animation.

This is a great way to show which areas of the construction site are currently active.

The Show Task List radio button toggles whether the Gantt Chart is displayed while the Construction Zone Manager is open. The Gantt Chart and the Construction Zone Manager must be displayed so that the user can select both a task and a Zone at the same time.

Enable Zone Edit must be active in order to remove or add selected zones to tasks.

Adds the zone selected in the Contsruction Zone manager to the selected temp task. When added to a temp task zones displays during the duration of the task.