Work Rate Calculation
Learn how to use the Work Rate Duration Calculation menu to calculate task durations with BIM data
|
|
|
|
|
|
|
|
---|---|---|---|---|---|---|---|
The Rate of Work app in Fuzor allows users to calculate the expected duration of a task using data stored in the BIM properties of objects assigned to tasks. | |||||||
Use the Rate of Work button in the 4D Toolbox to open the Work Rate Duration Calculation Menu app. | |||||||
The Work rate Duration Calculation menu displays all work rate calculations in the file. The Create button adds a new work rate calculation to the list associated with the task that is currently selectedin the gantt chart. Each work rate calculation can be furthur filtered down to apply to a subset of the objects assigned to the assoicated task. In order do be included in the work rate calculation the objects must contain a given value in a specified BIM parameter. In the example above only objects with the “Structural Foundation” Category are included in the calculation. The Classification selects a BIM property to use to filter the objects The Value drop down menu is used to select a value to filter the objects The Unit drop down menu specifies an additional BIM parameter that is used for the calculation. In the example above the Volume is used to for the calculation. in this case the total volume is calculated for appropriate objects and mulitplied by the Rate of Work / Hour factor. The Calculate button processes the rate of work calculations and updates associated tasks. The Calcuated Duration column displays the workrate calculation. |
Workrate Management
Learn how to view workrate calculations of specific tasks.
|
|
|
|
|
|
|
|
---|---|---|---|---|---|---|---|
Workrate Calculations are stored in the Calculated Duration Column in the Gantt Chart. This column displays the total of all calculated durations associated with the tasks. | |||||||
In some situations more information is needed to understand the workrate calculation or how several work rate calculations are added together. The Calculated Duration column can be selected to diplay more information about the workrate calculation | |||||||
The button in the Calculated Duration column can be selected to open the Tasks’s Work Rate Details menu. this menu displays more information about the workrate calculation. | |||||||
Each separate calculation is stored as a separate entry. Specific information about how the duration is calulated is displayed and is updated when durations are recaluclated. |